FAR 52.232-25: Prompt Payment (Net 30 & Statutory Late Interest)

Official federal procurement regulation analysis, contractor performance obligations, and risk mitigation strategies for small businesses.

REGULATORY CONTEXT

What It Means in Plain English

Official Acquisition.gov Text ↗

Enforces the Prompt Payment Act, requiring federal agencies to pay contractor invoices within 30 days of receiving a proper invoice, or automatically add Treasury-set late payment interest penalties.

Where This Clause Appears in Federal RFPs:

Mandatory in all federal fixed-price supply and service contracts.

Mandatory Statutory Requirements

  • 30-Day Payment Clock: Payment is due 30 days after the designated billing office receives a proper invoice or 30 days after agency acceptance of work (whichever is later).
  • Automatic Interest Penalty: If payment is late, the government MUST automatically pay interest at the U.S. Treasury rate without the contractor needing to request it.
  • 7-Day Defective Invoice Notice: The agency must notify the contractor within 7 days of invoice receipt if an invoice is defective or missing required details.

Contractor Compliance Obligations

  • Include all 10 proper invoice elements: Contract Number, Order Number, CLIN, Item Description, Quantity, Unit Price, Shipping/Payment Terms, UEI, Banking Info, and Submitter Contact.
  • Submit through the agency's designated electronic invoicing portal (e.g. IPP, WAWF/PIEE).
⚠️ Audit Trap & High-Risk Pitfall

Submitting an invoice without the exact CLIN or with an incorrect UEI causes immediate rejection and resets the 30-day clock.

Frequently Asked Questions About FAR 52.232-25

What happens if an agency pays my invoice on Day 45?

The agency must pay interest for the 15 days of delay calculated at the published Treasury prompt payment interest rate, included in the payment disbursement.

Related Procurement Clauses

FAR 52.219-14

Limitations on Subcontracting (The 50% Rule)

When a small business wins a set-aside contract, it cannot simply broker the deal to a large business or non-qualified subcontractor. The prime contractor (and its similarly situated small business teammates) must perform at least a specified minimum percentage of the contract value or labor cost.

View Analysis →
DFARS 252.204-7012

Safeguarding Covered Defense Information & Cyber Incident Reporting (CMMC / NIST 800-171)

Requires all Department of Defense contractors and subcontractors handling Covered Defense Information (CDI) or Controlled Unclassified Information (CUI) to provide 'adequate security' by implementing the 110 security controls of NIST SP 800-171, record a score in SPRS, and report cyber incidents within 72 hours.

View Analysis →
FAR 52.204-27

Prohibition on a ByteDance Covered Application (TikTok Federal Ban)

Strictly bans the presence or use of TikTok or any application developed or provided by ByteDance Limited on any information technology used by contractors in the performance of federal contracts, including personal devices used under BYOD policies.

View Analysis →

Verify Solicitation Clauses with AI

BidGovAI reads Section I of your target RFP, extracts every referenced clause, and builds an automated compliance matrix so your capture team never misses a statutory landmine.

Start 14-Day Free Trial →Browse All FAR Clauses →